A rear dormer loft conversion takes 6 to 8 weeks on site. Design, structural calculations and approvals take another four to eight weeks before work starts.
What happens before work starts?
Survey, drawings and structural calculations take two to four weeks. Building regulations plans are then submitted, party wall notices served, and a lawful development certificate or planning application made if needed. Party wall notices need up to two months' notice unless neighbours consent sooner.
Weeks 1 and 2: structure
Scaffold goes up, materials are lifted to roof level, and the steel beams and new floor joists are installed, working through an opening in the roof and not through the house.
Weeks 3 and 4: dormer and roof
The rear slope is opened, the dormer frame built, and the roof covering, cladding and windows fitted. The aim is to be weathertight by the end of week four.
Weeks 5 and 6: stairs and first fix
The ceiling below is opened and the new staircase fitted, usually in two or three days. Electrics, plumbing and insulation follow, then plasterboard.
Weeks 7 and 8: finishing
Plastering, second-fix electrics and plumbing, bathroom fitting, doors, skirtings and decoration. Scaffold comes down once the outside is complete.
What can cause delays?
Weather during the two weeks the roof is open, late changes to the design, slow responses to party wall notices, and discoveries such as undersized existing joists. A realistic programme allows for some of each.